Poolside PID

Project Name

Poolside

Designer/s

@dominic.harrison @Alinta Lim

Project Deliverable

Design, develop and commercialize a luxury floating chair

Start Date

Dec 11, 2021

Target Launch

Post Summer 2023

Target Price Range

$1000AUD

Internal Resource Est.

0.25 0.5 FTE During Design & Dev Project length = 9 - 12 months

Project Budget

$10,000

Exp. CAPEX Cost

 

Product Proposition

Currently KING LIVING offers an outdoor range, David King has expressed his interest in expanding this range, especially as King Living grows and creates its presence into international markets. KING LIVING proposes to include a floating chair & sun lounger in the outdoor living range expansion, Mimicking the “Award Sofa” as a throw back to the heritage of KING LIVING.

The floating chair must be of a “premium” quality, therefore chasing a high price tag, accordingly to the KING brand. After a previous project exploring the idea of an inflatable floating chair it has been understood to attain a “premium” status it is desired that the chair is a drain through, this extending the life of the chair, as failure through membrane puncture is avoided. It has been expressed that the floating chair & sun lounger would also feature in a range expansion, range expansion is detailed below. The initial floating chair design is preferred to go to market for the Australian 2022/23 summer period.

This Project includes:

  • Floating chair

  • Floating sun-lounger 

  • Option to include platform base

 

Range Expansion:

  • Beanbag double sunlounger,

  • Beanbag 2 and 3 seaters

  • Beanbag ottoman

  • Platforms being a possible design direction

  • Expand range to indoor version with same options

 

Update: Moved away from the award sofa form. Two new forms will be explored, “modified award sofa” and “curved form”

 


Range Gap

 

KING Living currently does not have an outdoor sofa or floating range. This floating chair will be a completely new sector for KING, which expands the outdoor range.

 

 

 


Requirements for Success

What is the target requirements to make this a successful project?

Requirements

Requirements

Floats and balanced

Comfortable

Moderately easy to remove from pool when wet

Easy drying

Ease of removing and inserting bean bags

Beans bulge consistently

Ease of getting in and out of the chair in water

Lifespan of X years under normal use @Patricia (Unlicensed) need to ask marketing if this is important

Ease of filling the bean bags

Drain through feature

Holds 1 person up to 150kg

Chlorine, salt and UV resistant

Fail safe for bean bag puncture (bean spillage)

Market leader in floating pool furniture

 


Key Risks & Considerations

What are the key risks involved in the project?

e.g. manufacturing risks, design complications, bottlenecks in the timeline, commercialization risks, brand discrepancies

Key Risks

Mitigation Plan (Concept Refinement Phase)

Key Risks

Mitigation Plan (Concept Refinement Phase)

Water furniture compliance?

Found ISO 25649-3 which details floating water safety, will follow standard to produce a safe product

Maximum wet weight

Drain through feature and ergonomics of handles to be continually developed, reduce excess volume

Is there any regional safety requirements?

To do review of regional safety requirements

Is this item subject to any specific tariffs and/or duties?

To do quick review of tariffs and duties, mainly based around the beans

Longevity/warranty

Less of a concern now product is not an inflatable, will have supplier guarantees on materials and fabrics

Balance & float

To be a development focus

Attaining premium KING feel

Create targeted comfort zones

Go-to market date

Have design freeze by XXXX

If it isn’t a FLOCK item how do buyers view and purchase?

Releasing only Chair and sun-lounger, should have showroom space available to FLOCK

Alignment of brand strategy narrative

Not inflatable, lesser of an issue. Competitor premium brands do alike.(Roda, Natuzzi) @Patricia (Unlicensed) marketing team to think about sustainability

Bean filling

KING living to fill the bags at production center. Involve Engineering team early to create production process and space

Unsure Production Location

Liaise with Ed and Tony on the most appropriate manufacturing facility

Material and construction strength and longevity

Discuss with Engineering, could complete tests around zipper burst strength, stitch strengths, abrasive resistance ……..

Material Supply

Secure supply early as possible. Freeze fabric selection as early as possible


Design, Develop & Test

 

What Must be Designed?

  • Product care and information tags

What must be Developed?

  • Form & aesthetics

  • Drain through feature

  • Fabric Patterns

  • Foam form & layering

  • Internal beanbags

  • Foam exoskeleton in fabric cover

  • Handles & grips

  • Floating ability

  • Stability and balance in water

  • Comfort in & out of water

  • Engineered support - ergonomics

  • Zoned support

  • Bean selection & characterization

What must be tested?

  • Float

  • Balance

  • Comfort

  • Longevity (chlorine, salt, UV degradation)

  • Drain through

  • Beans

  • Safety

  • Pools standards


Manufacturing Scope

 

Manufactured In-house

  • Fabric & sewing

  • Foam Cutting

  • Beans filling ( bean bag filling room)

 

 

 

Procured Externally

  • Beans

  • Foam

  • Fabric

 

 


Resourcing Estimates

Project Length

Project Length

 

 

P I

r n

o t

j e

e n

c s

t i

t

y

 

Less than 3 months

3 - 6 months

6 - 9 months

9 - 12 months

12 months +

High

Designer = 1.0 FTE +

Medium

High

Very High

Very High

Very High

High-Med

Designer = 0.75 - 1.0 FTE

Medium

High

High

Very High

Very High

Med

Designer = 0.50 - 0.75 FTE

Low

Medium

High

High

Very High

Med-Low

Designer = 0.25 - 0.5 FTE

Low

Low

Medium

Medium

High

Low

Designer = 0 - 0.25 FTE

Low

Low

Low

Low

Medium


Initial Concept Ideation & Sketches

 


360 Marketing

  • For marketing to complete

  • 360 Marketing plan

 

 

 


Sustainability

•How is this product going to hint towards the sustainable future KING strives for?

 

 

 

 

 


Return on Investment

 

PROFIT & LOSS (By Year)

0

1

2

3

4

5

6

7

8

9

Expected COGS (BOM cost)

 $ 180.00

 $ 180.00

 $ 180.00

 $ 180.00

$ 180.00

$ 180.00

 $ 180.00

$ 180.00

 $ 180.00

 $ 180.00

Expected Sales QTY

0

1500

1575

1654

1736

1823

1914

2010

2111

2216

Expected Logistical Costs

$ 75.00

$ 75.00

$ 75.00

$ 75.00

$ 75.00

$ 75.00

$ 75.00

$ 75.00

$ 75.00

$ 75.00

Average Sale Price

 $ 790.00

 $ 790.00

 $ 790.00

$ 790.00

$ 790.00

 $ 790.00

 $ 790.00

 $ 790.00

$ 790.00

$ 790.00

Product Margin 

 $                      -  

 $        802,500.00

 $        842,625.00

 $        884,756.25

 $        928,994.06

 $        975,443.77

 $      1,024,215.95

 $      1,075,426.75

 $      1,129,198.09

 $      1,185,657.99

Marketing Costs

 

 

 

 

 

 

 

 

 

 

Development Costs

 $ 10,000.00

 

 

 

 

 

 

 

 

 

CAPEX (Tooling & Machinery purchases)

 

 

 

 

 

 

 

 

 

 

Project Costs

 $          10,000.00

 $                      -  

 $                      -  

 $                      -  

 $                      -  

 $                      -  

 $                      -  

 $                      -  

 $                      -  

 $                      -  

 

 

 

 

 

 

 

 

 

 

 

Net Cash Flow

-$ 10,000.00

 $ 561,750.00

 $ 589,837.50

 $ 619,329.38

 $ 650,295.84

 $ 682,810.64

 $ 716,951.17

 $ 752,798.73

 $ 790,438.66

 $ 829,960.60

Cumulative Cash Flow

-$ 10,000.00

 $ 551,750.00

 $ 1,141,587.50

 $ 1,760,916.88

 $ 2,411,212.72

$ 3,094,023

$ 3,810,975

$ 4,563,773

$ 5,354,212

$ 6,184,173

Discounted Cash Flow  (NPV)

-$ 10,000.00

 $ 520,138.89

 $ 505,690.59

 $ 491,643.63

 $ 477,986.86

$ 464,709

$ 451,801

$ 439,251

$ 427,049

$ 415,187

Cumulative Discounted Cash Flow

-$ 10,000.00

 $ 510,138.89

 $ 1,015,829.48

 $ 1,507,473.10

 $ 1,985,459.96

$ 2,450,169

$ 2,901,970

$ 3,341,221

$ 3,768,270

$ 4,183,457

 