28/07/22 Meeting Minutes
Date | 28th of July 2022 |
Attendees | @Pearson Bulmer (Unlicensed) @Ned Volk (Unlicensed) |
2. Project Updates:
Heritage
Completed | To Do |
---|---|
@Pearson Bulmer (Unlicensed) to continue chasing up Shiyang for mechanisms
| Table Mechanisms being airfreighted |
John’s fabricated frame | @Pearson Bulmer (Unlicensed) to Present options to DK plan for 3/08 |
@Pearson Bulmer (Unlicensed) CNC’d ply wood | @Pearson Bulmer (Unlicensed) to review finishes for timber And previous work already done |
| @Pearson Bulmer (Unlicensed) to design manufacturable leg cover |
| @Pearson Bulmer (Unlicensed) to completely assemble table, proportions and aesthetic sample |
Tasman Chair
Completed | To Do |
---|---|
@Dylan Dasey (Unlicensed) to CAD steel frame and timber legs | John’s to finish fabrication 29/07/22 |
@Pearson Bulmer (Unlicensed) organised steel frame to be fabricated | @Pearson Bulmer (Unlicensed) to order more oak for legs |
@Ned Volk (Unlicensed) to organize leather | @Pearson Bulmer (Unlicensed) to get Allan to upholster by 3/08/22 |
@Pearson Bulmer (Unlicensed) followed up Secco on whether they have an aus timber supplier. They do not, and would have to organize our own supplier. | @Pearson Bulmer (Unlicensed) to get Silvio or Phil or Allan to foam the chair |
| @Pearson Bulmer (Unlicensed) to manufacture legs |
| @Ned Volk (Unlicensed) to call matilda veneer back |
|
|
Myco
Completed | To Do |
---|---|
| @Pearson Bulmer (Unlicensed) to approve design |
| Change height to use same bolt size as Apero |
| Product will come in 2 leg colours & 4 tabletop colours |
| @Pearson Bulmer (Unlicensed) to email Jane to follow up on leg manufacture |
|
|
|
|
|
|
Magnolia
Completed | To Do |
---|---|
@Pearson Bulmer (Unlicensed) updated CAD model and sent to parawood for sample of chair | @Ned Volk (Unlicensed) to create timeline |
| @Tony (Unlicensed) finding Thai timber table supplier |
| @Pearson Bulmer (Unlicensed) to send new cad to Secco for sample |
|
|
marketing will need sample in February for photoshoot
Seymour
Completed | To Do |
---|---|
| With GL R&D team, @Pearson Bulmer (Unlicensed) to continue to follow up |
|
|
Other
Completed | To Do |
---|---|
Team to go through risk mitigation for key risks highlighted | @Lauren Eskin (Unlicensed) is on Holidays |
|
|