Ponti 07/07/22 Meeting Minutes

Date

7th of July 2022

Attendees

@Pearson Bulmer (Unlicensed) @Ned Volk (Unlicensed)

 

2.    Project Updates:

Heritage

  • 2 pathways of development

    • Of the shelf mechanism

    • Mechanism Developed in house

Chosen To go for off the shelf mechanism

  • Pearson has requested for GL to find mechanism, numerous variants have been short listed. Will be a few weeks till units arrive in Turrella

  • @Pearson Bulmer (Unlicensed) Pearson To CAD steel frame. Jon’s to fabricate

  • @Pearson Bulmer (Unlicensed) to create Finn legs in Turella

  • Aiming to have Prototype completed in 2 weeks for a design freeze

 

  • 2 Stages of release

    • Fixed release

    • Dynamic release

Approved

 

  • Tuscany to be revised for the fixed version

    • Named the “Tasman”

    • @Ned Volk (Unlicensed) To chase new Leather options

    • @Pearson Bulmer (Unlicensed) to work on CAD for chair

Tasman Approved

 

  • @Pearson Bulmer (Unlicensed) to send timber suggestions to @Ned Volk (Unlicensed)

  • Chairs for marketing will be manufactured in Turrella

  • @Ned Volk (Unlicensed) to find appropriate person within KING to source Australian timbers

Myco

  • @Pearson Bulmer (Unlicensed) to approve design once it arrives in airfreight, test in Showroom

  • Could release in 2 heights for minimal work, @Ned Volk (Unlicensed) Ned to run it by marketing

  • Product will come in 2 leg colours & 4 tabletop colours

  • @Ned Volk (Unlicensed) to check with marketing on where they see this can fit in with marketing and best time to release

  • @Pearson Bulmer (Unlicensed) to email Jane to follow up on leg manufacture

Magnolia

Seymour

  • With GL R&D team, no actions

Other

  • @Ned Volk (Unlicensed) to update PID with new locked in direction of project

  • Team to go through risk mitigation for key risks highlighted

  • @Lauren Eskin (Unlicensed) is on Holidays