Ponti 07/07/22 Meeting Minutes
Date | 7th of July 2022 |
Attendees | @Pearson Bulmer (Unlicensed) @Ned Volk (Unlicensed) |
2. Project Updates:
Heritage
2 pathways of development
Of the shelf mechanism
Mechanism Developed in house
Chosen To go for off the shelf mechanism
Pearson has requested for GL to find mechanism, numerous variants have been short listed. Will be a few weeks till units arrive in Turrella
@Pearson Bulmer (Unlicensed) Pearson To CAD steel frame. Jon’s to fabricate
@Pearson Bulmer (Unlicensed) to create Finn legs in Turella
Aiming to have Prototype completed in 2 weeks for a design freeze
2 Stages of release
Fixed release
Dynamic release
Approved
Tuscany to be revised for the fixed version
Named the “Tasman”
@Ned Volk (Unlicensed) To chase new Leather options
@Pearson Bulmer (Unlicensed) to work on CAD for chair
Tasman Approved
@Pearson Bulmer (Unlicensed) to send timber suggestions to @Ned Volk (Unlicensed)
Chairs for marketing will be manufactured in Turrella
@Ned Volk (Unlicensed) to find appropriate person within KING to source Australian timbers
Myco
@Pearson Bulmer (Unlicensed) to approve design once it arrives in airfreight, test in Showroom
Could release in 2 heights for minimal work, @Ned Volk (Unlicensed) Ned to run it by marketing
Product will come in 2 leg colours & 4 tabletop colours
@Ned Volk (Unlicensed) to check with marketing on where they see this can fit in with marketing and best time to release
@Pearson Bulmer (Unlicensed) to email Jane to follow up on leg manufacture
Magnolia
Seymour
With GL R&D team, no actions
Other
@Ned Volk (Unlicensed) to update PID with new locked in direction of project
Team to go through risk mitigation for key risks highlighted
@Lauren Eskin (Unlicensed) is on Holidays