Date | Week commencing : 26th June 2023 |
Project Updates:
GREEN : No more changes
AMBER: Possibility for changes
RED: Will more than likely change
BLUE : New Project
DESIGNER | PROJECT | CATEGORY | Actioned | To do | CAMPAIGN ASSIGNED | CAMPAIGN DATE | FLOCK TARGET DATE | DEVELOPMENT STATUS | RELEASE STATUS | |||||
---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|
PALLINO PORTABLE | LIGHTING | ongoing | Tarmac will start prototyping new anodised colour options slowly. 2 x colours picked out- she will reach out to anodising supplier to help figure out how to specify then get samples in to TU. Stock will be late, should be confirmed how long the lead time before sale period starts. Delayed customer orders by 3 weeks, will confirm again with Coffey by 30/06. Spare parts- Mina is awaiting costings from Coffey, packaging complete- once costings come in and SPN confirmed by GL, Hussain will help get them into SAP. | FLOCK on the water, arrive by Post Autumn Purchase order split into 4 sections, next 3 orders can have colour changes based on market feedback. | POST AUTUMN | May 1st | Completed |
| GREEN | |||||
FARO PENDANT | LIGHTING | ongoing | Final samples arrived in TU. Product development 100% complete. Aura sofa accessory - needs a name update, Michele is working on it as Faro might be problematic. Michele working on PO, customer purchase has already started. Still delayed, need to push this. Decided to go with lead time storing in GL. Mina requested invoice for the PO from Coffey, once we pay they can start production. | WINTER- air freight for flock would be required- and stock for immediate release? | Jun 15 | Production week 26th March |
| GREEN | ||||||
LUNA TIMBER | BARSTOOL | Done, counter stool also available now. Will remove from task list. Spare parts process underway with Hussain. Awaiting Yanqiu in R&D. | AUTUMN | Mar 23 | ETA Mar 25 |
| GREEN | |||||||
ELEVATE | HOME-OFF | ongoing | Sample for Elevate is on it’s way to TU. Cecco top sample received. Awaiting rest of product costing from GL. Xiangu leg sample also completed, awaiting costings from Xiangyu and JiaShun. Consider sending Elevate top to new solid timber suppliers. Underway with Eto as a comparison. 10% increase approx. on cheaper timbers, 17% saving on AmWl. Aesthetic design in solidworks for the leg sleeve is done, Mina 3D printed a leg sleeve, will install once sample arrives in TU. | SUMMER- delayed by DK | Sept 14 | early July |
| RED | ||||||
SOLAIR ALU POCKET Accessory (with shade/turn dial shape) | ACCESSORY | ongoing | Samples received from supplier for review - review sent and feedback received, they will implement updates, new sample underway. Still no lead time info. Only black is suitable for deep etch as silver is unlikely to be ready in time. Deep etch team can manage with this as long as they have a silver swatch to use for photoshop. Still not shot. Costing is with Michele (still haven’t heard back), expect Coffey to complete Sample by 23/06- DIDN’T ARRIVE Not suitable to add lighting colour update at this late stage. Looking to see if the supplier has an option to change from ‘cool to warm’ light and can’t implement possibly integrate with Home Automation Systems - this will cost $200K, Dylan need to discuss with SLT. Coffey also possibly has an option but with King App is preference. DK has requested that we don’t do the expensive option, possibly a King Lighting App only which is managed by someone else. Spoke to Coffey re other app options, he had ideas and companies suggested, awaiting info from Coffey to email (still awaiting). Then we can go back to DK with 3 options, no brand, rebrand and Ingenuity. In terms of production readiness for flock is very much PO dependent once we get feedback from pricing. Costings arrived, sent to Michele, but still awaiting tooling (new off tool parts) but will let Michele/Damo know about initial costings. Haven’t heard back from Michele regarding this yet. | WINTER- even with airfreight will be late due to production lead time. Product sample not completed yet. Push to Post Winter or beyond. Mina to confirm. | - | - |
| RED | ||||||
HELIO PENDANT | LIGHTING | ongoing | DK meeting happened, a lot of feedback from DK which has changed the course and brief. Weight is important (consider plastic or reduce alu material). Mechanical vertical movement mech remote operation direction now (single ceiling point), Jordan will start the conversation with Coffey. App integration is dumbed down for cost purposes- see above (Solaire). @jordan will did some work on the modular version to explain to DK the number of wires visible and complexity of electrician set up. Will render one version and send to DK. Idea is individual pendants that magnetise together but are powered separately (electrician joins in ceiling to use one switch on the wall). Need an end cap- put aside until gap in firefly timeline. | DELAYED | N/A |
| RED | |||||||
ETO DESK V2.0 | HOME-OFF | ongoing | Timber accessories all samples complete. On a boat to TU. Handful of adjustments with the team, Mina managing in a document. TF discussion happened- he’s open to updates, with no1 request being solid timber top. Preferencing new top style. All is resting on pricing for the time being, if solid top can be accommodated then production almost ready. If veneer then will need resampling. Need pricing feedback first. - New suppliers have come back with pricing approx 10% increase . on cheaper timbers, 17% saving on AmWl. Aluminium charger ring, feedback to supplier has been completed- no issues from supplier and Tom is happy. Samples in TU. Mina will rebuild on the new sample and then show TF again. | paused | June 15 | early April |
| RED | ||||||
ETO TBL LAMP | HOME-OFF | ongoing | Sample arrived, 95% sample, assessment by Tom required and Tanya talk to DK. Oak colour is wrong. Update with Tom completed, Coffey will resample and answer questions. With Coffey- Need costings from Coffey- expectation 30/06 to send to Michele so can update DK on costs. Mina sent light samples back to Coffey. | paused- see above | June 15 | early April |
| RED | ||||||
ETO TASK LIGHT | HOME-OFF | ongoing | Sample arrived, 95% sample, assessment by Tom required and Tanya talk to DK.- battery missing. Need to make it a non-tipping product after Tom assesses it. Oak colour is wrong. Update with Tom completed, Coffey will resample and answer questions. Need to send the lights abck to Coffey again to save time on re prototyping. See above light. | paused- see above | June 15 | early April |
| RED | ||||||
LUNA MESH BARSTOOL & COUNTER STOOL | OUTDOOR | BAR STOOL: Sample reviewed by CW. The new new sample looks more accurate, but awaiting CW to sit on the sample before starting tooling. COUNTER STOOL: Shorter frame approved and will be incorporated into Timber stool, same base concept used for mesh stool. Two stools have been air freighted for photography. Tooling lead time 40-45 days. Awaiting first batch quantities confirmation from Michele prior to confirming the lead time for first batch. | POST WINTER!- Spring? | Aug 3 | 16th May |
| RED | |||||||
LUNA UPH | BARSTOOL & COUNTER STOOL | ongoing | BARSTOOL & COUNTER STOOL: Dome consideration to add to seat top. Cut dome in production for flock. Flock on the way to showrooms, Mina working on spare parts. Mina to look at updating tooling to include the dome. Ask Shiyang to 3D scan the new seat with dome in it so that we can update the foam tooling mould. Shiyang finding a 3D scanning supplier. | POST WINTER | Aug 3 | 16th May |
| GREEN | ||||||
ELEMENT EXTENSION TBL | OUTDOOR | Ongoing | New concept. DK to approve concept/range plan. Waiting on Tanya looking over the brief. (Need to discuss with DK.) Note: design direction from DK is with a D end. Extension mech spec sheet needed by the supplier. Mina do concepts by next week to review. Set meeting to go through it Wednesday 26th April. Need to consider whether it’s important for next years outdoor release. Tanya Rechberger to find out if we still want it as a priority for next year, then need to get Mina started on it slowly now. | Not assigned- paused. Need proper brief. |
| NEW | ||||||||
SWIVEL DINING CHAIR | DINING | ongoing | Initial prototype with timber back has been reviewed by DK - feedback was works well with ETO desk, need a more dining based version that can double as home office. Tanya Rechberger talk to DK re priority! | Not assigned- paused until time allocation completed. |
| NEW | ||||||||
LIGHTING GALLERY | VM | stopped | Michele spoke to Jackie/Vickie/Emily on requirements Michele feels that in store over product display is a better solution and feasible post Michael discussion. Michele will discuss with DK if he’s in agreement. Design of gallery on pause until DK conversation as may not be required. Not a project as company agreed to install into ceiling. | Not Assigned | - | - |
| RED | ||||||
DIRECTORS CHAIR | OUTDOOR | Documentation shared to Shiyang, tooling and BOM cost due from Shiyang 23/06. Cross brace costed in stainless and Aluminium. BOM prelim arrived: missing some items need more info but looking close to 335RMB already. Awaiting GL feedback for more detail. Will ask if they have ideas on where to make savings. Investigating in house production, Miao has responded on Mandrel bending machinery, Mina to get back to him enquiring on more machinery that would be involved for this to become a product in GL. Sling cover sample 1 completed. Highlighted comfort issues in frame form. Zipper was used need to test strength, also fabric stretched. Highlighting that we need stronger batylene, or layer up with stronger fabrics quilted. Plan to go to prototype tooling ASAP (after 1 month extrusion tooling ready). This then needs to tested in press tools, with aluminium bounce back would expect issues, but minimal 2 weeks for tweaking. This is with press tool starting at same time as extrusion tooling. Lounge chair solidworks completed and sent to Shiyang to sample after normal chair. Even minimising the sling cover prototyping time (1 week) we are in early September for production start. Even if we start tooling after quoting immediately, we are still mid July for off tool components. Need to work out using off tool components all the small mechs at this point as well. Even if we buy off the shelf extrusion, we need to make 4 weeks for press tool + 2 weeks for tweaking. Mina not interested in weeks of workshop time to make the photoshoot items which will not be useful for product release and will slow that down. A little bit of downtime while awaiting tooling completion. Cheap mesh sample- Mina is currently testing the mesh with 150kg to test if stretch and seams are suitable. Order the extrusion tooling after quotations returned. CAPEXs will need to be raised. Mina modelled counter and Bar heights for form, will show DK and get his opinion before considering if he starts to resolve footrest yet or wait. | Unassigned as yet | Aug 3 | Early May |
| RED | |||||||
FIREFLY- outdoor lantern | OUTDOOR | Brief - portable, charging, ip rated, fabric integration for softer feel. Concept stage- conversation with Tanya once prototypes are completed. Brief update permanent outdoor version, so needs higher IP rating. DK confirmed wants plug in charging. Coffey has a lot of experience with outdoor lights, will get back to Jordan with feedback to his questions, will ask for response by 30/06. Jordan Ruchalski (Unlicensed) Working on 3D samples for photo shoot. Explore more options for hiding surface texture for the shoot from 3D printer- no solve as yet. For shoot- 1 lamp promised, up to 4 if possible. LEDs arrived, look good. DK meeting confirm 31/05- charging near house rather than in garden space. Plug in charger. Start with smooth finish consider adding ribs/texture down the line. Make the shapes more mix and match between the sizes (squat and elongated). Upmarket sound solution to incorporate in (ask Coffey). Wifi compatibility decided due lower cost, as well as fixed on/off switch possibly with Pallino operation capabilities. Looking to see if the supplier has an option to change from ‘cool to warm’ light and can’t implement possibly integrate with Home Automation Systems - this will cost $200K, Dylan need to discuss with SLT. Coffey also possibly has an option but with King App is preference. DK has requested that we don’t do the expensive option, possibly a King Lighting App only which is managed by someone else. Spoke to Coffey re other app options 20/06 (Mina will ask), he had ideas and companies suggested, awaiting info from Coffey to email. Then we can go back to DK with 3 options, no brand, rebrand and Ingenuity. | Post spring | Aug 3 | Early May |
| RED | |||||||
BAR CABINET | CASED GOODS | Commercialisation stage of this product to be considered with Michele first. It has been started, Priorities need to be defined. | Deprioritised | |||||||||||
CASED GOODS | CASED GOODS | Commercialisation stage of this product to be considered with Michele first. | Deprioritised | |||||||||||
HIGH-LOW floor light | LIGHTING | Commercialisation stage of this product to be considered with Michele first. | DePrioritised | |||||||||||
DESIGNER | PROJECT | CATEGORY | Actioned | To do | CAMPAIGN ASSIGNED | CAMPAIGN DATE | FLOCK TARGET DATE | STATUS | ||||||
ADELAIDE | BEDROOM | Injection moulding completed. Veneering pricing underway. Veneering samples fading too fast compared to GL samples, Dylan finding out if issues. Alinta will follow up Dylan again for standards. Bed instructions are critical. Dom will do a back up video but possibly CS can handle the video. Packaging sent over. On hold for time being until design finalised again. Working on extending sizing rollout after flock. California King- not for US flock, but will be offered- GL for mattress, and other beds. SAP preparation underway. On hold for time being until design finalised again. Feasibility of corner has been proven, just working on producing it neatly. Top of bed technique, needs to be decided based of Cabana best solution. 8 weeks for spring production readiness. Inner frames- 35x20 tube was strong enough. Pins to connect the two frames together- need to test, Alinta to manage, trial this week. Alinta jump test completed- pass on to James to prove it. Mosquito net machine sewing tension still not right, pattern will need to be checked after tension issues solved. | WINTER | June 15 | Early April. Qty: 15 pieces |
| AMBER | |||||||
DUNE | CASE | DK approved current leg design and low style (not in line with mattress height), Alinta will expand the range as necessary and work with JiaShun on further updates. (Draw mech etc) Attachment method redesign. Ask James about testing criteria. | WINTER | June 15 | Early April. Qty: 15 pieces |
| RED | |||||||
CABANA | OUTDOOR | Roof structure- redesign plan B solution underway, requires a cut out, laser welding might work, but might not- awaiting Wichai. For photography, wont see that area so send any option.- still to solve for production. Sun lounge frame for GL - GL has made first sample, not powder coated. Thailand is making sample for photoshoot. It’s a working prototype on one side. Almost production ready. Cabana seat cushion reticulated seat insert completed cover sample to do this week. Still looks poor, working through it. Powder coat samples has been powder coated in a satin finish but doesn’t match GL so purchasing to keep trying to match GLs over time. Alinta Lim will check with James P. about whether the TH outdoor foam is suitable. In progress- Gam couldn’t get all of the details as requested, Alinta to follow up James. for handover to purchasing. Knock-ins will be tooled in China- Shiyang So far James is confident with flock production, James will follow follow up with a few long term questions with supplier. Knock-ins will be tooled in China- Shiyang is okay on that. 2 of 3 confirmed and approved by Alinta. 3rd one is the roof cap. Photography will be 3D print. Outer Frame design solved just production of frame, to be solved which has lot to do, Alinta involved in following up. Roof fabric- Alinta organised to have it airfreighted over for photoshoot.Sort out the horizontal sewing issue. Finalised today 26/06. Still awaiting confirmation from Seb N and DK to make a call on Cabana fabric. | / | POST WINTER | Aug 3 | Early May Qty: TBA |
| RED | ||||||
GAZEBO | OUTDOOR | Scope stage, new project suggestion by DK | Not assigned | - | - |
| NEW | |||||||
GARDEN CHAIR + OLIVE TABLE | OUTDOOR | Making cover with Allan- update 2.0 is waiting for Allan, stainless steel chair has arrived and is surprisingly comfortable even without cover. | POST WINTER | Aug 3 | Early May Qty: TBA |
| RED | |||||||
PLATELETT TABLE | OUTDOOR | Adjustable height with manual turning mech. Material selection to be discussed with DK.
| POST WINTER | Aug 3 | Early May |
| RED | |||||||
Plateau Outdoor | OUTDOOR |
| SPRING | Aug 3 | Early May |
| AMBER | |||||||
ISSHO MARBLE OCC. TBL | CASE | Gloss or honed finished to be sampled with supplier when GL is back. Honed finish is DKs preference. Consider thinner finish on carrara than marquina. Legs in marble? | Not assigned | - | - |
| ||||||||
ISSHO ASYMETRICAL DNG TBL | DINING | Redesign top shape, DK not happy with current form yet. DK suggested prototype using the builder from his house, Alinta has asked Michael, awaiting a response from builder. | Not assigned | - | - |
| NEW | |||||||
New organic 2.0 OCC. TBL | CASE | New base option to suit Organic Sofa by Zara Need to follow up Dom on updating. Make marble version. | WINTER | June 15 | Early April |
| RED | |||||||
POS FABRIC SAMPLE RACK | N/A | Timeline is ASAP, currently fabric samples stored in cupboards. Alinta is on this and it seems a waste of her time consider design intern on this. | Not assigned | ASAP | ASAP |
| NEW | |||||||
SPEAKER BRACKET UNIVERSAL | Universal bracket after Adelaide Bed | Not assigned | Not assigned | NEW |
DESIGNER | PROJECT | CATEGORY | Actioned | To do | CAMPAIGN ASSIGNED | CAMPAIGN DATE | FLOCK TARGET DATE | DEVELOPMENT STATUS | RELEASE STATUS |
---|---|---|---|---|---|---|---|---|---|
1977 | SOFAS | Magic joiners are not functioning without frame alterations, we think investigating velcro joiners is out because of DK. Ratchet foot cup/leg loop solution and the steel extra screwing into the frame underside. Ordered rubber bands and leg velcro joiners for testing, hopefully one of these options works out as a temp flock solution at the very least. Currently the cup is underway but off the shelf solution is the priority. Stefan understands the issue on the legs lining up issue and he needs to play around with the CAD as we can’t open the newer files. Live project tracker has been put together by Seb, Wichai needs to populate and then we will have access. Working on product range expansion. White frame of chaise with arm due 3rd May. Urgently working on Accordian style love seat first. Still awaiting feedback from Frank.
Design registration disclosure -sent with all products except the ottoman. Cylindo: Hussain has everything from Seb and is on his plate. Deep etched images- Seb has updated the deep etch drawing. Future point- Liaise with James Pudney on load testing/quality. | WINTER | June 15 | Early April |
| AMBER | ||
MYCO | CASE | Production finished, flock underway. Spare parts should be completed, Seb will double check. Will show at managers meeting. Seb to locate the tables. Quality testing underway with James P. | POST WINTER | 5th August | Mid May |
| AMBER | ||
OUTDOOR C TABLE | OUTDOOR | Vague brief given to Sebastian by DK. Brief which will start with investigations, can Seb start with it in between other projects, Seb will set that meeting. On peripheral. | Unassigned | ||||||
1977 OUTDOOR SOFA | OUTDOOR | Drain through fabric outdoor version of sofa.
| AMBER | ||||||
POOL FURNITURE | OUTDOOR |
| |||||||
ARC FLOOR LIGHT | LIGHTING |
| |||||||
Outdoor Sofa | Pipeline projects, pitching ideas as per DK convo | ||||||||
Indoor Occasional Chair | Pipeline projects, pitching ideas as per DK convo |
...
DESIGNER | PROJECT | CATEGORY | Actioned | To do | CAMPAIGN ASSIGNED | CAMPAIGN DATE | FLOCK TARGET DATE | DEVELOPMENT STATUS | RELEASE STATUS | ||
---|---|---|---|---|---|---|---|---|---|---|---|
AURA | SOFA |
| WINTER | June 15 | Early April |
| GREEN | ||||
Aura Outdoor | OUTDOOR |
| |||||||||
AURA FLOAT | FLOAT | PAUSE |
| ||||||||
ARC TASK | LIGHTING | ongoing |
| Unassigned | June 15 | early April |
| RED | |||
QUAY CHAIR | DINING | Scanning completed? this was to be the guide to CAD for foam molding and steel. Video or the process shared with the team? Discuss with DK regarding the Quay Chair foam moulding already completed. | Not assigned | - | - |
| RED | ||||
QUAY BAR | BAR STOOL | Sample received by GL. Next steps?
| Not assigned | - | - |
| RED | ||||
CURVE | SOFA | DK confirmed the design direction. Will transfer to Zara when she has time after Aura and Aura outdoor. Update brief, post Milan- run past DK. | SUMMER? | 26/12 | 24th September |
| AMBER | ||||
JASPER 20th | SOFA | FLOCK on the water. Deep Etch/CGI to be scheduled. AI, Product Cards to be done. VM/Brand to confirm how many packages. Enter new SAP code for Curve with light, and new smart pocket. Changeover this week- go and check the lights. | AUTUMN | Mar 23 | Jan |
| GREEN | ||||
KATO BED | BEDROOM | Concept to get started. Don’t have a brief yet. | Not assigned | - | - |
| RED | ||||
KATO V2.0 | SOFA | Firmer seat design completed. Enter into SAP? | Not assigned | - | - |
| RED | ||||
AMARA CHAIR SOFT | DINING | DK completed in GL, need to follow through production
| |||||||||
LUNA OCCASIONAL INDOOR CHAIR UPDATE | OCCASIONAL | Charles wants to update the comfort of the inside of the occasional chair, DK has approved the process start. Trying to get Charles to manage the prototyping process. Have found chair for using on sampling. Tanya Rechberger to bring up to design area. Shiyang searching for latest Luna indoor chair file to pass on to CW. | |||||||||
Super soft foam exploration | SOFA GENERAL | DK wants to explore using a super soft foam which is high density to replace dacron in some circumstances. Seen it at Cassina. The team found a foam to replace LT48, rejected because they didn’t understand the purpose of the foam, as a backup supplier. It wasn’t as good as LT48 so they rejected it. Perhaps they misunderstood the brief. Tanya to ask DK for more details. Tanya Rechberger discuss with Michele and DK re the designer and priority of DKs new sofa design. Also ask MD for foam sample from Italy if possible. |
...
DESIGNER | PROJECT | CATEGORY | Actioned | To do | CAMPAIGN ASSIGNED | CAMPAIGN DATE | FLOCK TARGET DATE | DEVELOPMENT STATUS | RELEASE STATUS | |
---|---|---|---|---|---|---|---|---|---|---|
HEIRLOOM CHR | DINING | Plastic injection moulding for legs have not been sent from GL, PO issued today. Production starting on the chairs today- sign off from DK was yesterday. Gam made some updates to the patterns including automotive closure. Requested packaging testing, awaiting feedback. Push again for ITSA test, drop tests have failed apparently but Ryan doesn’t have up to date information. Die lines of chair packaging with marketing at the moment. DK sent a video of the product and some images, Ryan will try to Beta photoshop app for managers meeting. Assembly instructions- air freight chair sample from TH for Adam to create instructions. | AUTUMN | Mar 23 | Feb Qty: 26 |
| RED | |||
HERITAGE FIX TBL | DINING | Second and final Sample from UZ home underway, we pivoted them away from this priority over to extension table. Could possibly review the required updates on an ext. table. TBC closer to date. | POST SPRING | 4th November | 13th August |
| AMBER | |||
HERITAGE EXT. TBL | DINING | GL Making sample now. Working on multiple avenues at the moment, custom supplier parts and in house version. DK pushed for in house again, Shiyang has big concerns which have been communicated with DK. We will push ahead in any case and Cecco make a sample of timber components. Working to tight timeline as updated by Team Ponti here 2023 PROJECT CALANDER Ryan&Pearson.xlsx DK signed off on 90 degree timber veneer and on table mechanisms. Shengsheng sample is quite good- but Ryan is awaiting more detailed feedback in the report before we can commit to the product for flock. Expect back 26/06. Had some supplier (UZ) hiccups on timeline issues currently looking at 3-4 weeks late for UK, CA- 2-3 weeks late, VicQld 1-2 weeks late. Will assess again closer to the and do our best to claw time back. UZ a bit disappointing but Shengshen is promising so far. The timber work is decent. Motor addition has been put on hold, working on gas pop up lift sample. Ryan to work on the concept alongside Shen for fastest solution to be found. Latest quotes from UZ home for manual extension table are walnut $2974 AUD and $2345 AUD for Congo/Smoked oak. Shangsheng is approx. $400 cheaper for walnut version. In GL- installation of mechanism - Ryan will start Shiyang on this. Ryan will speak to Shiyang about the learnings from the assembly of the Shengshen sample. | POST SPRING | 4th November | 13th August |
| AMBER | |||
TASMAN CHR | DINING | Yabo sample is underway, DK has approved with improvements to the seat inlay. GL to send a steel seat frame to Yabo. Plan to have a seat insert manufactured in GL and assembled in Customers home. +/- 3mm tolerance on the chairs is achievable which will assist in this process. Aware it’s very risky and will be putting a lot of work into minimising risk in order to get max benefit. | SUMMER | May 4 | Mar |
| AMBER | |||
MAGNOLIA TBL | DINING | design stage TBA Samples with suppliers soon. DK has approved to go ahead with suppliers (change timber horizontal to steel tube). Details and drawing to work through, requote with steel. -Consider as an extension table | POST AUTUMN | May 4 | Mar |
| RED | |||
MAX 2 | SOFA | Project on pause. DK mentioned on Monday Jan 23 what the status was on this project. | Not assigned | - | - |
| RED | |||
LIGHT TIMBER COLOUR OPTION/ Master stain update | Trying to create King master colours across the board, as well as new lighter colour. Pearson has ideas on using Ash instead of Red Oak across the board, it’s cheaper and more durable. Pearson will speak to GL team to get some sampling moving along. Cecco is remaking some samples, Oil based was used instead of water based, so needed to redo. Fingers crossed it will be faster this time (not 6 weeks like last time). Only Cecco currently looking at light timber option as they are our main solid timber supplier and they use the best water based finished. Veneer sample master underway with one supplier currently. Pearson will follow up. GL purchasing team assisting with this to try to bring all finishes into line together to match colours better. UZ samples underway to ensure timber finishes from them match. | |||||||||
NEW SOFT FLEX ARM SOFA | Tanya Rechberger to call DK and confirm the project kick off with Ryan and Pearson, Pearson holiday starts next week. |
...